40 CFR Part 62, Table 5

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
Affected facilitiesIncrement 1Submit final control planIncrement 2AwardcontractsIncrement 3Begin on-site constructionIncrement 4Complete on-site constructionIncrement 5Final compliance
Affected facilities that commenced construction modification, or reconstruction after June 26, 1987:
1. Emission limits for Hg, dioxin/furanNAcNAcNAcNAc11/12/99 or 1 year after permit issuance d e
2. Emission limits for SO2, HCl, PM, Pb, Cd, opacity CO, NOXJanuary 11, 199905/18/9911/16/9911/19/0012/19/00.

a Table 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in table 6 of this subpart.

b As an alternative to this schedule, the unit may close by December 19, 2000, complete retrofit while closed, and achieve final compliance upon restarting. See §§ 62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.

c Because final compliance is achieved in 1 year, no increments of progress are required.

d Permit issuance is issuance of a revised construction permit or revised operating permit, if a permit modification is required to retrofit controls.

e Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.

[63 FR 63202, Nov. 12, 1998, as amended at 65 FR 33468, May 24, 2000]